Our Projects – Romania
AZOMURES Chemical Plant
- Frame contract for engineering services – 2021–2027
- Ammonia 3 & Ammonia 4 Units revamp projects – Detail Engineering
- Design of six new pipe systems operating in creep conditions, in Ammonia 3 unit – Detail Engineering
- Design of new pipe systems operating in creep conditions, in CET 2 unit – Detail Engineering
- Etc.
Ploiesti - OMV PETROM Petrobrazi & Petrotel LUKOIL Refineries
- Frame contract for repair and maintenance engineering services – 2015–2026
- MFO 0.5% sulphur production in Petrobrazi Refinery – Full engineering
- Revamp of wastewater treatment plant – Detail Engineering
- Revamp of the utilities networks (refinery gas, natural gas, air & nitrogen) – FEED Phase
- Isomerization unit revamp – Detail Engineering
- New LPG truck loading ramp – Detail Engineering – 2012
- New DGRS unit, civil & steel structures – Detail Engineering – 2011
- Revamp of Hamon cooling water system – FEED Phase
- Sewage system revamp – FEED Phase
- Fire fighting system revamp – FEED Phase
- Etc.
ARPECHIM Refinery, Pitesti (OMV PETROM)
- Optimization of the existing firefighting water system in the Refinery and Terminal area – Detail Engineering
- SWS incinerator compliance at FCC Unit – Basic Design & Feasibility Study
- Low density polyethylene pneumatic transportation system revamp – Detail Engineering
- Gases desulphurization, sulfur recovery & sour water stripping units – Assessment Level II
- Revamp of cooling towers – Feasibility Study
- Optimization of the fire fighting water network system in the Petrochemical area – Feasibility Study – 2008
- Implementation of ON/OFF valves – Feasibility Study
- FCC (Vacuum Distillate) Hydrotreating – Detail Engineering
PETROMIDIA Refinery, Constanta (ROMPETROL)
- Frame contract for engineering services in Petromidia Refinery & Petrochemical Plant – Full Engineering – 2019–2025
- Computational measurements through geometric precision and interpretation of compaction measurements at Refinery Plant installations and Petrochemical Plant
- C3+ Hydrocarbons Recovery Unit – Feasibility Study
- Delayed Coker Unit revamp – Closed Blowdown System – Detail Engineering
- Hexane delivery pipeline to berth no. 9B – Detail Engineering
- HDV Unit reconfiguration – Detail Engineering
- Revamp of landfill oily sludge separation processing plant – Detail Engineering – 2007
- Revamp of polypropylene unit – 80,000 t/y – Full Engineering
- Loading/unloading system and cryogenic storage facilities – Full Engineering – 2005
- Revamping of wastewater treatment plant – Detail Engineering
- Etc.
PETROTEL LUKOIL Refinery, Ploiesti
- Technical expertise and rehabilitation project for steel structure 09-FV11
- Sulphur Recovery TGT Unit – Detail Engineering
CHIMCOMPLEX – Ramnicu Valcea Platform
- Improving the energy efficiency of brine membrane electrolysis plants in Rm. Valcea plant – Feasibility Study
- Polyurethane foams recycling unit in Ramnicu Valcea platform – Feasibility Study and FEED
- Flue Gas Desulphurization Unit at Govora Power Plant – Detail Engineering
- VCM capacity extension to OLTCHIM – Basic Engineering
- Lindane Plant at OLTCHIM – Detail Engineering
- Wastes incineration & HCl recovery at OLTCHIM – Detail Engineering
- Revamp of Electrolysis IV Plant at OLTCHIM – Detail Engineering
CHIMCOMPLEX – Borzesti Platform
- Improving the energy efficiency of brine membrane electrolysis plants in Borzesti plant – Feasibility Study
- 120,000 tonnes/year Chloride (caustic soda) Unit – Detail Engineering
- Modernization of the Electrolysis III installation – Detail Engineering
Contesti
- 4000 m³ LPG fuel depot and bottling station for BUTAN GAS ROMANIA – Full engineering
Aviation fuel storages designed by PETRODESIGN
- Otopeni, Timisoara, Cluj, Bacau, Campia Turzii, Fetesti
Nis Petrol Romania
- Collection and dispatch station in Teremia South location - FEED and Detailed Engineering
- Collection and dispatch station in Teremia North location - FEED and Detailed Engineering